Home City Government Service Department Bexley 2010 Street Projects
Bexley 2010 Street Projects Print E-mail

 

FAIR AVENUE

 

Mon. Aug 23rd - Fri. Sept. 3rd  No parking on the north side of the street from Remington to Gould.  Driveways will not be accessible during the day, but there will be parking on the south side of Fair Ave. 

Tues. Sept. 7th-Fri. Sept. 17th  Same as above on the south side of the street.

 

PLEASANT RIDGE AVE. - ASTOR TO THE CURVE

Mon-Aug 16th    Installation of new water main will begin.  Paving work will follow in September.

Beginning tomorrow, the intersection of Pleasant Ridge and Astor will be closed for 2-3 days for a water line replacement.

 

 

 Repairs on the following streets are scheduled to begin during the month of September

Bryden Road from Parkview to Drexel

Plymouth Avenue from Roosevelt to Merkle

Elm Avenue from Columbia to Dawson

 **Please note that access to driveways will be maintained as much as possible.  There may be  some inconvenience during the hours of 7:00am to 6:00pm. 

 
 

Service Contacts

Al Mathes | Service Superintendent
Andy Bashore | Maintenance Superintendent
Anne Farley | Executive Assistant
Bill Harvey | Service Director
Mark Moore | Parks Supervisor

Location and Hours

City Hall