FAIR AVENUE
Mon. Aug 23rd - Fri. Sept. 3rd No parking on the north side of the street from Remington to Gould. Driveways will not be accessible during the day, but there will be parking on the south side of Fair Ave.
Tues. Sept. 7th-Fri. Sept. 17th Same as above on the south side of the street.
PLEASANT RIDGE AVE. - ASTOR TO THE CURVE
Mon-Aug 16th Installation of new water main will begin. Paving work will follow in September.
Beginning tomorrow, the intersection of Pleasant Ridge and Astor will be closed for 2-3 days for a water line replacement.
Repairs on the following streets are scheduled to begin during the month of September
Bryden Road from Parkview to Drexel
Plymouth Avenue from Roosevelt to Merkle
Elm Avenue from Columbia to Dawson
**Please note that access to driveways will be maintained as much as possible. There may be some inconvenience during the hours of 7:00am to 6:00pm.
|